Kansanshi copper pre-feasibility study

The Kansanshi Joint Venture (KJV) between Bateman Project Holdings Limited and Kvaerner Metals, conducted a pre-feasibility study to develop a potential large scale mining operation at the former ZCCM’s Kansanshi copper mine north of Solwezi in Zambia’s north-western province on the border of the Democratic Republic of the Congo. The work was done for Cyprus Amax Minerals Company, Eagle wood, Colorado, USA.

The ultimate objective of the pre-feasibility study was to determine whether to go forward with a final ‘bankable’ feasibility study. Schedules for possible construction, pre-commissioning, start-up and production were prepared with capital and operating cost estimates.

During this pre-feasibility phase a diamond drilling and metallurgical mapping programme characterized the ore and identified the potential for economic mining and beneficiation. Process flow sheets will be developed for further evaluation. The available power, water and transport and other infrastructure was also evaluated. General arrangement drawings were prepared, showing the location of the mine, process and ancillary facilities, for a mine complex capable of producing approximately 100 000 t/yr of copper.

KJV provided the project management, engineering and administrative services required. Several consultants were involved in different aspects of the study, including the geotechnical and tailings dam design and environmental impact (SRK), hydrology (Water Management Consultants), mine planning and ore reserve evaluation (IMC). The metallurgical test programme was conducted by Hazen Laboratories.

The Kansanshi mine has a history going back some 400 years when high grade copper oxide ore was mined from outcropping veins. Claims were first pegged on these ancient workings in 1899 and copper mined sporadically, at first from open-pit and later from underground workings. Open-pit mining activities were resumed by ZCCM in the late ‘70s and only recently terminated.

The pre-feasibility study commenced in September 1997. The drilling results were encouraging and preliminary resource estimates were prepared to support conceptual design development and preparation of preliminary capital and operating cost estimates. The work was completed early in 1999.

For more details, please contact Mr Ian Martin, Engineering Manager, on +27-11-899-3114.
basemetals@batemanengineering.com

View PDF