AC Furnaces track record
(Click on the heading for
more information)
BATEMAN
joins forces with COMETVA SA to market the latest technology in electrode
columns for AC furnaces
BATEMAN has signed a collaboration agreement with COMETVA SA, providing
clients of both companies the option of utilising the new hydraulic
electrode-clamping device from BATEMAN, together with forged copper
electrode components, sold under the brand COFOR, from COMETVA SA.
This agreement therefore provides the industry with access, through
a single source, to the latest technology and improvements in electrode
columns.
Bateman
electrode column for UMSL, India
BATEMAN has been awarded a contract to supply an electrode column
to Utkal Manufacturing & Services Ltd (UMSL) in India for their
new 27 MVA submerged-arc, high-carbon ferrochrome furnace.
New
furnace electrode-clamping device offers improved
process control
BATEMAN's new electrode-clamping device for furnace installations
offers the ferroalloy industry significant benefits, including no
lubrication required after installation and minimal maintenance; low
operator involvement; minimal wear on moving parts and much faster
slipping rates for better process control, compared to the previous
electro-mechanical drive units. An order for the new device has already
been received from an international client.
Numerical
modelling reduces engineering costs
The benefits of numerical modelling in quickly
verifying design improvements and optimisations, thus reducing the
time from design to installation, was again demonstrated in recent
work by BATEMAN on a new electrode pressure ring with an improved
heat-dissipation capacity. The ring is for application on Söderberg
electrodes in AC-arc furnaces.
Ferrometals'
Furnace 4 upgraded to 60 MVA
BATEMAN has completed an upgrade of Ferrometals' Furnace 4 (F4) in
Witbank, RSA, for Newsam Pty Ltd (a joint venture between Samancor
and Poschrome) to increase the furnace's production capacity from
100 000 t/yr of ferrochrome to
125 000 t/yr.
SA
Ferrochrome exceeds criteria in performance tests
The newly installed furnaces and sintering plant at SA Ferrochrome
exceeded performance and design criteria in performance tests recently
completed by BATEMAN. In addition, following commissioning, monthly
targets were increased constantly.