
The building housing the modified sizing facilities at Springvale Colliery. |
Springvale coal ROM modifications
The run-of-mine (ROM) coal handling and sizing facilities at Springvale
Colliery, previously rated at 900 t/hr, have been upgraded by Bateman
Kinhill, Sydney. The project involved the conceptual and detail design,
supply, installation, site modifications and commissioning of an extension
to the existing sizer building and its new and modified equipment.
Bateman Kinhill was awarded the project as a result of its experience
in this type of work and its ability to come up with the right conceptual
solutions to the perceived problems. It was also able to commit itself
to a short construction period at the lowest cost.
Several problems were associated with the reclamation, conveying and
sizing of the coal and with tramp iron, trash and oversize material
in the coal stream from underground.
The stockpile reclaiming equipment had to be modified to eliminate frequent
blockages and a new trash and sizing screen was installed to separate
the coal into size fractions for crushing or by-pass; oversize material
is rejected to a collection area.
Because only the size fraction of the coal requiring crushing is now
sent for sizing, one sizer (of the two existing twin shaft units) can
cope with the duty. Modifications were made to the mechanical equipment
and controls to enable automatic changeover of the sizers in the event
of failure or blockage. This provides a backup facility at the most
vulnerable point in the coal processing path.
Crusher tooth life has been enhanced by providing a controlled distribution
of material over the full crushing zone of the sizers.
The effectiveness of tramp iron removal has been improved by relocating
the two existing tramp iron magnets to a position in the circuit behind
the trash and sizing screens, where the material passes along slow moving
conveyor belts with small material profiles.
The new and modified facilities were constructed with the existing plant
in full operation and the changeover was accomplished during an extended
weekend shutdown. The above measures resulted in improved plant availability
and an increase in capacity of 15 %.
More details may be obtained from Eric Fletcher on
+27-11-201-2300 or email coal@batemanengineering.com.
VIEW PDF
|