Plant automation at Blair Athol

Bateman Kinhill has been engineering and project managing the automation of the fixed plant and the two 4,000 t/hr bucket wheel stacker / reclaimers on the Blair Athol Coal Project. The objective is to reduce the manning requirements at the plant and improve equipment availability and information gathering.

Blair Athol Coal, the largest coal mine in Australia, is located near Clermont in Central Queensland and produces approximately 11M t/yr of coal. The bulk is exported to joint venture partners in Japan. The Blair Athol Coal Project is a joint venture between Queensland Coal Pty Limited, a subsidiary of RioTinto, (57 %); Arco Coal Australia Inc., Delaware, U.S.A., (18 %); Arco Resources Limited, Australia, (14 %); E.P.D.C. Pty Limited, Japan, (8 %); and J.C.D. Australia Pty Limited, Japan, (3 %).

Bateman Kinhill's part in the project involves the replacement of a mimic panel and obsolete PLC (programmable logic controller) programs with a full S.C.A.D.A. (supervisory control and data acquisition system) / PLC operator interface system and modifications to the stacker / reclaimers to enable unmanned operation. The installation had to be done with limited production loss. The technology includes fibre optic communications through cable reelers, including PLC control and closed circuit TV data.

The new automation system has enabled the PLC program to operate the stacker / reclaimer within its design limits. Thus operator error has been eliminated, productivity has been improved and maintenance costs reduced.

On the basis of this experience, the improvement in productivity on its own would fully warrant the automation of any stacking and reclaiming facility.

The work on the automation system commenced about two years ago and is now being completed with a brief shutdown of the plant to implement the reclaimer software modifications. The total capital cost of the project, including the on-line coal quality management system, is approximately Aus$ 6M.

For further details, please contact Eric Fletcher on +27-11-201-2300 or email coal@batemanengineering.com.