
Vibrating feeders below the stockpile feeding run-of-mine (ROM) ore
to the crushing and screening plant.

A BATEMAN belt feeder under the crushed product silo feeding minus 8
mm material to the milling plant.




|
Bafokeng Rasimone Platinum Mine Concentrator Plant
A 200 000 tonne/month concentrator at the Bafokeng Rasimone Platinum
Mine (BRPM) as been established for Amplats Management Services (Pty)
Ltd just outside Rustenburg, North West Province, RSA.
Project Scope
This greenfields project involved the design and detailing, procurement
and commissioning of all equipment (excluding the crushing and screening
plant). The major equipment included primary and secondary mills; flotation
plant; concentrate and tailings handling circuits; water and air reticulation
systems; and reagent storage areas. The project also covered the coarse
ore stockpile and the storage silos for mill feed. The entire site area
was prepared with bulk earthworks, terracing, drainage and sewage reticulation
and roads, buildings and associated infrastructure.
Process Circuit
The run-of-mine (ROM) ore is delivered from two shafts by means of an
overland conveyor and is fed to a conical stockpile suitable for three
days' storage. Vibrating feeders draw from the stockpile and deliver
the ROM ore (300mm x 300 mm x 500mm) to the crushing and screening plant.
A primary jaw crusher, vibrating screens and five gyratory crushers
allow the feed material to be reduced to minus 8 mm and this is conveyed
to the two mill feed silos. The primary mill is a 20 ft (6,10 m) ball
mill with classification by means of a cyclone bank. The overflow from
this unit is fed to the primary rougher flotation cells (10tank cells
of 50 m³ each) with their associated cleaner and recleaner circuits
(20 m³ and 10 m³ tank cells). Recovery of platinum from the
tailings stream is further improved using the secondary milling and
flotation plant. The 16 ft (4,88 m) ball mill feeds a similar flotation
plant of roughers, cleaners and recleaners as has been described above.
The final tailings stream is thickened in one of two high rate Bateman
Ultrasep thickeners before being pumped to a tailings dam some 4 km
distant using a multi-stage centrifugal pump system. The high specific
gravity and the special pumping considerations required preliminary
test-work by the CSIR.
The platinum concentrate is thickened using a conventional thickener
and subsequently de-watered by means of a Larox filter press. This material
is conveyed to one of two storage bins and then via belt feeders into
trucks for despatch to the Waterval Smelter at Rustenburg.
Special Features
The new mine and concentrator plant were developed on land owned by
the Royal Bafokeng Nation. Amplats has a unique working relationship
with Royal Bafokeng and looks forward to long term co-operation. A condition
of the project was that the Royal Bafokeng Nation and local suppliers
be included in the provision of contracts, labour and services as far
as possible and to this end BATEMAN and other contractors formed alliances
and services which assisted with the empowerment of the communities
and the transfer of skills and training. This project followed an extremely
tight, fast-track programme. It was planned to a high level of detail
and controlled down to every drawing to the sub-contractors and to the
supply and delivery of every item of equipment to site. The construction
was undertaken in a systems-oriented manner so that hot commissioning
of the plant could follow the construction phase smoothly and during
commissioning all services and utilities were available plant-wide.
All the structural steelwork for the project was designed so that it
could be galvanised and obviate the need for on-site painting after
erection. The galvanised steelwork will provide appropriate protection
against the elements for the anticipated 25 year plant life.
Project schedule
BATEMAN undertook the original feasibility study for the project. The
project was awarded in mid-September 1998. Cold and hot commissioning
of the plant's wet section was completed and handed over to the mine
in December 1999. The plant is performing well with the milled ore tonnages
ramping up to design throughput by mid-2000.
Further details may be obtained from: Steve Burks, Managing Director,
Bateman Metals, on +27-11-899-2756 or email pgm@batemanengineering.com
|