Safety Success at Kasese
An exemplary safety record was achieved with only one minor disabling
injury occurring during the whole Kasese project. A total of 3 012 749
working hours was required to construct the cobalt process plant about
17 km north of the equator in Western Uganda. The disabling injury frequency
rate (DIFR) was thus 0,33 per million man-hours.
The client was Kasese Cobalt Company Limited, a subsidiary of Banff
Resources of Canada. From the outset of the project the safety of the
personnel was given very high priority. BATEMAN has a proud safety record
on projects, many of which are in remote and difficult locations. Almost
25 million man-hours have been worked on BATEMAN managed projects over
the past few years. The average DIFR recorded for these projects is
1,22 per million man-hours.
Six major and three minor contractors drawn from Denmark, Kenya, Uganda
and South Africa were employed on the project, with a peak complement
of almost 1 000 personnel on site. The locally recruited workers were
inexperienced in construction work and almost all of the contractors
staff constituted a high safety risk and therefore required on-the-job
safety training.
The BATEMAN safety policy, amended to suit conditions in Uganda, was
included in the tender enquiry documents and thus became a contractual
requirement. This ensured that the contractors had an obligation to
comply and on the project it was policy to rigidly enforce a rigorous
safety plan. While gentle motivation and awards for compliance were
applied, any transgressors were first warned verbally. Repeated or deliberate
contraventions of safety regulations were, however, not tolerated.
The strategy, in the first instance, was to ensure that all personnel
on site had passed a safety induction course and had undertaken to comply
with safety regulations. Even senior head-office staff had to undergo
induction before being permitted to enter.
The BATEMAN Safety Manager ensured that contractors held five-minute
talks with the workers (called toolbox talks) every morning on selected
subjects. It was compulsory for all contractor staff to attend these
talks and the quality of the talks was continuously monitored by the BATEMAN
Safety Manager.
Joint weekly safety meetings were attended by representatives of all
the contractors who were reminded regularly that ultimately they were
responsible for the safety of their workers. Safety meetings were also
held weekly within the contractors organisations.
This recipe obviously worked well! One million man-hours free of disabling
injuries were achieved twice and the project was well underway to achieve
the two million mark, with 1 704 393 disabling injury-free hours having
been recorded since the projects only lost time incident.
View PDF