Upgraded flotation-circuit at BMA’s Gregory
Coal Mine
Bateman Engineering N.V. has upgraded the flotation circuit
of the coal-processing plant at the Gregory Crinum Coal Mine near
Emerald, Queensland, Australia for the BHP Billiton Mitsubishi Alliance
(BMA) by replacing the existing conventional circuit with new flotation
technology. BMA is Australia’s largest coal producer and a leader
in the international coal industry.
The project covered the installation of a flotation circuit comprising
five Microcell flotation columns, 4.9m in diameter and 10.5m tall,
and a 30m diameter clean-coal thickener.
This flotation circuit, which has increased the yield of coking coal
at the mine by approximately 6 %, refines a slurry of the minus 750
µm fraction of the Gregory’s Lilyvale seam to produce
a coking coal with an ash content typically around 5.5 % and as low
as 4.5 %. The higher quality of the fine coal emerging from the circuit
also enables the coarse fraction to be washed in the existing plant
at a higher density, increasing the overall yield of the combined
coking-coal product.
The clean-coal thickener assists with dewatering and controls the
feed density to the existing belt-filter units. The latter were previously
designed, installed and commissioned by Bateman Engineering at the
mine.
During construction, 240 t of structural steelwork was installed and
about 4,500m of piping used, comprising basalt lined and extra strength
steel as well as high-density polyethylene (HPDE) piping. Electrical
and control systems to run and automate the operation of the circuit
were also provided.
The design concept embodied in the project was that the upgraded circuit
should work harmoniously with the existing plant and comprise readily-available
standard equipment with which BMA was familiar. The focus was on ease
of operation and ease of maintenance. The upgrade would also have
to be cost effective, with low initial CAPEX and ongoing operational
cost.
The project was undertaken under a AUD24 million lump-sum turnkey
(LSTK) contract. It presented the usual challenges associated with
having to install a new facility alongside an existing operational
process plant.
Work on the detailed design for this project commenced in November
2005 and the initial stages were fast tracked to permit the earth
works to start and the existing services to be diverted on the site
and the off-site fabrication to commence by April 2006. Site work
on the structural, mechanical and piping components commenced in July
2006 and the upgraded circuit was successfully commissioned.
In accordance with BMA’s zero harm policy, there were no lost-time
injuries.
Contact Glen Koperberg, Project Manager, on +61-7-3320-3306, or email
glen.koperberg@batepro.com.au for more details on the project.
VIEW PDF
©
Copyright BATEMAN 2007