| 
Bateman BQR flotation cells for Syama gold mine in the fabricators yard.

A Bateman BQR Flotation Cell which will be supplied complete with
interconnecting piping, interconnecting walkways and blowers.
|
Increasing international demand
for Bateman BQR flotation technology
Bateman Engineering is supplying its BQR flotation cell technology
to an increasing number of international projects, and a widening
range of clients, with recently-awarded contracts including Hindustan
Zinc in India, African Copper Plc - Dukwe Mine in Botswana and the
SOMISY SA - Syama gold mine in southeast Mali.
The contract for the expansion project of the Hindustan Zinc concentrator,
at Rampur Agucha Mines, Bilwara in India, marked the first time Bateman
Engineering had designed a flotation process for a combined lead /
zinc concentrator, a feature that required a number of banks of flotation
cells.
The cells comprised five BQR500 (50 m3) Zinc Rougher, seven BQR400
(40 m3) Lead Rougher and Scavenger, three BQR400 (40 m3) Zinc Cleaner,
seven BQR200 (20 m3) Zinc Cleaner and five BQR50 (5 m3) Lead Cleaner
Flotation Cells, complete with interconnecting piping, walkways and
blowers
The project is also a milestone in inter-company co-operation across
international borders. The design was done by the Bateman Engineered
Technologies division in South Africa, whilst the fabrication and
installation will be done by Bateman India. Supervision of installation
and commissioning will be supported from South Africa.
Bateman Engineering is also responsible for the entire US$35 million
lump sum turnkey contract for Hindustan Zinc’s 1 million t/yr
concentrator expansion. This award was the Group’s first major
project in India and followed the opening, in June 2006, of Bateman
India as Bateman Engineering’s operational office to serve the
minerals and metals sectors in that region.
Hindustan Zinc Limited (HZL) is India’s only integrated zinc
company, operating from mine to finished metal and supplying around
73 % of India’s zinc requirements in 2005 to 2006.
The flotation cells for African Copper Plc - Dukwe Mine are being
supplied for two circuits, an oxide flotation circuit and a sulphide
flotation circuit, under contract to Senet. The contract covers the
design and supply of 16 BQR200 Rougher Flotation Cells, of which 10
are oxide and six are sulphide rougher cells, and 15 BQR50 Cleaner
Flotation Cells, of which eight are oxide and seven are sulphide cleaner
cells. The cells are being supplied complete with interconnecting
piping, interconnecting walkways and blowers. Bateman Engineering
is also responsible for supervising the installation of the cells.
The contract commenced in January 2007 and ex-works delivery is scheduled
for completion in August 2007.
The greenfields Dukwe Project is being developed by African Copper
Plc. The process plant, incorporating Bateman Engineering’s
well proven flotation process technology, will treat approximately
1 million t/yr of oxide, supergene and sulphide ores to produce saleable
copper concentrates expected to grade between approximately 30 % and
34 % copper. The plant is being built with an allowance for an expansion
to 2 million t/yr through the concentrator.
The contract for Syama Gold in Mali, owned 80 % by Resolute Mining
Limited and 20 % by the State of Mali, was awarded by GRD Minproc
and features Bateman Engineering’s first large scale installation
of
70 m3 flotation cells. The six BQR700 Rougher Cells are being supplied
with three BQR100 Cleaner Flotation Cells. The scope of the project
covers the design, fabrication and delivery ex works of the cells.
A particular challenge of this project is that, as it is an expansion
to an existing plant, the design of the new flotation circuit must
fit into the plant’s existing footprint. In addition, the client
is shipping the fully fabricated cells as break bulk to Mali, requiring
special attention from Bateman Engineering to the crating of the tanks
to prevent damage to the internal rubber linings. The project was
awarded in February 2007 and is expected to be completed in September
2007.
The Syama Gold project is owned by SOMISY SA who announced the redevelopment
of the gold mine in 2006, with an average gold production of 250,000
ounces per year from a resource of 6 million ounces.
The Bateman BQR Flotation Cells offer easy process optimisation through
purpose-designed levels of solids suspension, air rate adjustment,
easy froth-cone positioning and a stable pulp-froth interface. This
range of round tank flotation cells is used in roughing, scavenging,
cleaning and re-cleaning, unit and pilot cell applications to process
copper, zinc, platinum group metals, phosphates, graphite slag and
effluents. They range in size from 0.5 m3 (BQR5) to 150 m3 (BQR1500)
and feature a simple design which reduces the cost of spares, enhanced
power efficiency and a low maintenance cost.
For further information, please contact Bheka Majola, Manager, Process
Equipment, on +27-201-2300 or email SpecialisedEquipment@Bateman-bet.com.
VIEW PDF
©
Copyright BATEMAN 2007
|