Construction of the crusher building nearing completion. The apron slabs leading to the crusher's ore tip bin are on either side of the crusher. The excavation for the building is 30 m deep, with the crushed-ore conveyor leading into the bottom of the building from the bottom foreground. The 90 t gantry crane on its 18 m connecting span over the crusher has been painted red. The Bateman Scrubber, needed for dust suppression at the crusher, can be seen to the right of the gantry spanning the crusher.

The view of the new crushed-ore conveyor leading from the crusher. The conveyor intersecting the new conveyor is the old ore-feed conveyor which will be used to feed material from a potential future stockpile to the processing plant.

A 180 t haul truck backing towards the tip bin. The spare space on the right of the truck is the provision made for the larger new 240 t trucks.

 

Venetia diamond mine's primary crusher

The new primary crusher at the Venetia diamond mine near Musina in the Limpopo Province, RSA was commissioned successfully on schedule at the end of April 2006. This R232 million project to design, supply, install and commission a replacement primary crusher commenced in June 2004 and followed on earlier feasibility studies on the project conducted by Bateman Engineering. The project also included conveyors, a dust-extraction system, a workshop and an electrical substation for the plant.

Once construction was completed, the last stages of the project saw the work at the new crusher signed off as per the contract and quality checks made. The electrical substation was energised and all the working parts in the crusher and its infrastructure were tested. Material was then passed through the plant to ensure no spillage of material occurred and retrofits done where required.

As the crusher will have to cope with between four and five different types of feed material, ranging from very hard (40 MPa hardness) to wet and sticky, 1,000 t of each material was fed to the crusher. Each of these materials was handled as per specification.

Finally, the crusher was operated for a period of 72 hours during which it had to be shown that the crusher could process 1,200 t/h of mine feed.

Several innovations were included in the facility. The presence of large pieces of tramp iron in the feed, such as drill tubes up to 10m long and 150mm in diameter, has the potential to disrupt flow through the crusher by entering and bridging the channels in the crusher, resulting in feed blockages which would have to be cleared manually while production was halted. This possibility is minimised by providing the operator with a good view of the discharge of feed from the apron feeder into the crusher so large pieces of iron can be detected and removed from the crusher before a major blockage occurs.

A 90 t electrically operating travelling (EOT) crane with a 15 t auxiliary crane and a clam-shell bucket is provided so that the crusher can be maintained and material cleared out of the box surrounding the crusher and for the easy removal of any tramp iron.

The gantry carrying the crane had to be erected from both ends. The final 18 m span linking the ends fitted perfectly when it was lowered into position, a compliment to the attention to detail by the design, manufacturing and construction teams.

In facilities of this size, a separate access way is usually provided so that large items of equipment can be reached for maintenance. In the new crusher building, several access wells were provided, with the main staircase also being used as the service duct for the electrical cabling and piping, greatly facilitating access for maintenance.

Holding tanks at the top of the building mean that the lubrication oil for the crusher can be pumped rather than being transported in barrels, as has been done traditionally.

The ore feed to the crusher, containing large blocks of ore up to 1.5 m in size, are transported to the plant in 180 t haul trucks, with allowance in the design for future 240 t trucks.

These large blocks drop from a considerable height into the bin with tremendous impact. To ensure the bin is sufficiently robust, the liners were installed first, welded and then used as permanent shutters against which the concrete for the bin was poured. The concrete and the liners therefore fit closely, with no gaps between the two, reducing the risk of the plates being dislodged from the concrete.

The new crusher has been designed with an intended 20 to 25 year life span and will enable the mine to maintain production when the old crushing plant, located at the edge of the existing pit, is demolished to extend the pit life for a further 10 years after which operations will move underground. The change in the open-pit operations will increase the stripping ratio of waste-to-ore from about 2 to 1 up to as much as 10 to 1.

Bateman Engineering also assisted the mine personnel for a further month with minor technical problems that were revealed during the initial routine operations. The contract also provides for a subsequent 11-month guarantee period.

During this project Bateman Engineering was also engaged in a project to upgrade the infrastructure at Venetia (see BATEMAN Globe No. 53). These projects were undertaken subject to a partnership model agreed between De Beers and Bateman Engineering that was introduced in 2004
(see BATEMAN Globe No 39).

For further details of the Venetia primary-crusher project please contact James Nieuwenhuys, Senior General Manager, Diamonds, or Vincent Diesel, Project Manager, on +27-11-899-9111 or email diamonds@BatemanEngineering.com.