CAD rendering of the new Tubatse furnace feed system, showing the new feed conveyor, charge bin, charge chute assemblies, incorporating vibrating feeders, and the new water cooled furnace roof panels.

New furnace feed system for Tubatse Ferrochrome

Bateman Engineering has upgraded the furnace feed system at Billiton's Tubatse Ferrochrome plant in Steelpoort, Mpumalanga, RSA. The previous feed system comprised a number of conveyors feeding through the furnace roof directly into the furnace, while the new feed system consists of a conveyor feeding raw material to a new storage bin at a rate of 150 t/h.

The stored material is drawn from the bin by five vibrating feeders and fed into the furnace through seven feed chutes with water-cooled tips. The entire chute system is air cooled.

The challenge was to install the new system into the very limited space available in the existing building and position the new bin above an existing opening in the concrete floor. The structure of the building also had to be substantially strengthened to accommodate the additional load of the 120 t capacity storage bin.

This caused a height constraint and this, together with the position of the transferring conveyor, resulted in the need for an unusually-steep troughed conveyor, angled at 26°. The position of the feed chutes required a number of extremely long vibrating feeders up to 8 m in length.

This lump-sum turnkey project valued at R8.5 million arose out of a successful engineering study, conducted by Bateman Engineering, to investigate the possibility of replacing the furnace feed system at the plant.

A good relationship existed throughout the project between Bateman Engineering's project personnel and the client, ensuring that progress proceeded according to schedule.

For more information contact Dirk Schenk, General Manager Special Projects, on +27-11-899-2735 or email dirk.schenk@BatemanEngineering.com.