Cullinan cones plant replaced by DMS circuit
Bateman Engineering has replaced the old cones plant at De Beers'
Cullinan Mine near Tswane (formerly Pretoria) with dense-media separation
(DMS) circuits to recover diamonds from kimberlite feed. Two new BATEMAN
Mega twin-stream DMS modules, each with a capacity of 200 t/h, were
supplied to the mine.
Besides the fact that the cones plant was in need of replacement,
the installation of a new DMS circuit was motivated by the fact that
this newer technology would recover diamonds more efficiently and
reduce running costs significantly, primarily as the team required
to operate the new plant would be far smaller.
A major constraint of the project was the need to install the new
DMS circuits in a space between the existing buildings at the plant,
occupied by the four feed conveyors to the cones plant. As the removal
of these conveyors would affect the mine production, the project was
planned to minimise disruption and be accomplished in the shortest
time possible.
The modules were completely built and tested at the manufacturer's
yard before delivery to site, with special care being required as
the fit was extremely tight with little scope for adjustments once
the modules had been delivered.
The project commenced in April 2005, to be carried out in two phases.
While the first DMS module was being manufactured, the on-site task
was primarily to cut back two of the four feed conveyors to the cones
plant so space could be made for the module. The feed conveyors were
modified and a pipe conveyor installed to take the concentrate to
the final-recovery facility. The module was also linked to the existing
tailings system. The first module was in full production in the first
quarter of 2006.
During the second phase, the two remaining feed conveyors to the
cones plant were cut back, effectively shutting down this plant. Phase
one was effectively repeated to install the second DMS module, with
the exception that the pipe conveyor already installed also handled
the concentrate from this module. The whole upgrade was completed
in the second quarter of 2006.
Details of the project may be obtained from Robert Abate, General
Manager, Modular Plants
on +27-11-899-2238 or email modular@BatemanEngineering.com or Scott
Brebnor, Project Manager on +27-11-899-4960 or email modular@BatemanEngineering.com.