The Bateman Dynamic
Wet Scrubber treating the
off-gas from the furnaces at
the Rand Refinery.

Dust-collection system installed at Rand Refinery

Bateman Engineering has completed a R2 million lump-sum turnkey project for Rand Refinery Ltd to upgrade an existing dust-collection system by the addition of a new scrubber. The objective was to optimise the gold recovery from the particulate matter in the off-gases from the furnaces and minimise pollution of the environment.

The system comprises a Bateman Dynamic Wet Scrubber, with the appropriate ducting and other equipment, to scrub the off-gas from the furnaces and a Bateman Pinned-Bed Clarifier, to clarify the water after use in the scrubber. The new system collects and cleans off-gas from up to three of six refining furnaces prior to the off-gas being removed to the existing gas cleaning facility. The wet scrubber treats 1,600 Am³/hr of gas from the furnaces with a dust load of 7.5 g/Am³ at a scrubber inlet temperature of 45ºC.

The overall dust-collection efficiency is 99.5 % in the 1 to 2 micron particle-size range and a virtually solid-free, clean off-gas is produced. The scrubber requires 2.1 m³/h water, of which less than 3 % is lost due to evaporation and carryover in the clean-air discharge. The effluent water from the scrubber, containing about 0.55 % of suspended solids, is fed at a rate of 2.1 m³/h to the pinned-bed clarifier.

The clarifier produces an overflow containing less than 10 ppm of solids, which is recycled to the scrubber, and an underflow of thickened slurry at a rate of 25 l/min which is collected in a holding tank. Approximately 90 kg of solids are captured as filter cake (the supply of the filter organised by Rand Refinery) that is recycled to the furnaces. The flocculant addition system was installed by Rand Refinery in the beginning of 2006.

The contract for the project was signed in August 2005 and the new dust-collection system was commissioned successfully in November 2005.

The equipment is working as per specification after the installation of the flocculant dosing system. This was a brown-field project in which the new equipment had to be installed in a very restricted area in the plant with no interruption to production. A complicating factor was the high-level of security demanded at the site. The changeover from the existing to the new system was completed smoothly during one weekend.

Bateman Engineering was given the job ahead of several competitors because of the cost-effective solution offered to the problem of dust collection at the refinery.

More details may be obtained from Dirk Schenk, General Manager,
Special Projects, or Jan Barwise, Project Manager,
on +27-11-899-9111 or email SpecialProjects@BatemanEngineering.com.