PolyMet Mining awards BATEMAN
international metals feasibility study
BATEMAN has been appointed by PolyMet Mining Corp. as its coordinating
consultant for its fast-track NorthMet study in north-eastern Minnesota,
USA. The US$2M study concerns the feasibility of establishing a facility
to produce 33 000 t/yr of copper cathode at NorthMet, a low-grade
base- and precious-metals deposit which contains valuable quantities
of copper, nickel, cobalt, palladium, platinum and gold.
BATEMAN will take the lead in the process design, testwork and infrastructure
and retain consultants for the other elements of this definitive feasibility
study.
The contract will be carried out through BATEMAN's Brisbane, Australia,
office. Work commenced on schedule in mid-July 2004, under a series
of pre-contract work orders and is due to be completed by the third
quarter of 2005.
| BATEMAN was selected because of its considerable
experience in feasibility studies, its expertise in mineral-processing
plants for base and platinum group metals (PGM) and, in particular,
its expertise in the engineering, design, and construction of
pressure-leach circuits which are at the core of the proposed
process route for this project. BATEMAN applied this technology
in such recent projects as Gunpowder Copper in Australia and Sepon
in Laos. |
BATEMAN will provide the design- and cost-estimation services for
the metallurgical plant. As currently envisaged, the project will
process 25 000 t/day of ore from the NorthMet deposit to produce,
annually, 33 700 t of copper cathode, a nickel / cobalt hydroxide
containing 7 800 t metal and a PGM concentrate containing 120 000
oz (including gold).
The process route is defined by the PlatSol process and all
other unit operations are standard, subject to further pilot testing.
The re-utilisation of the large 100 000 t/day mothballed mill / concentrator
at the Cliffs-Erie facilities means that most of the key infrastructure
is already in place. The project, as it is currently envisaged, requires
the development of a mine at the NorthMet deposit. Ore will be truck
hauled from the pit to a rail transfer facility for rail haulage to
the primary crusher located at the Cliffs-Erie process plant approximately
10 km (6 miles) away.
Ore from the mine will be processed through the existing Cliffs-Erie
crushing / milling plant. New flotation circuits will be added and
a new hydrometallurgical plant constructed. This facility will produce
saleable products of copper cathode, a nickel / cobalt hydroxide and
a PGM concentrate. Waste streams resulting from the various processes
will be contained in established tailings impoundments. The construction
of the envisaged process plant will involve the following main activities
/ facilities:
Modifications to the existing comminution circuit, to produce a flotation
feed of P80 sizing (80 % passing the screen size)
of 200 µm, will involve the use of existing equipment and no
new structures are required for this section.
Construction of a new flotation and regrind facility in the existing
concentrator building. The regrind mills exist but all other concentration
equipment will be new with associated civil and structural work, piping,
electrical distribution and instrumentation / control.
The pressure-leaching circuit will be of an entirely new construction
in a purpose designed building and will comprise two 4,1 m x 24,6
m autoclaves and associated equipment including concentrate thickening
and storage.
Downstream from the pressure-leaching circuit are the unit operations
for solid / liquid separation and disposal of the leach residue to
lined cells in the existing tailings impoundment, PGM recovery as
a precipitate, neutralisation of the pregnant leach solution, copper
solvent extraction and electrowinning (126 cells of 54 cathodes each)
and the precipitation of a nickel / cobalt hydroxide.
Waste streams will be pumped to new tailings impoundments constructed
on the existing tailings dam. Infrastructure and ancillary services
will all be provided based on the re-utilisation of existing facilities
where possible. These will be refurbished and upgraded to meet the
new plant requirements and, where required, new facilities will be
constructed.
PolyMet Mining Corp. is an investor-owned junior mining company whose
principal asset is the NorthMet deposit, one of the world's largest
undeveloped low-grade base and PGM resources.
For further information, please contact Dave Arnold, General Manager,
PGM & Nickel, on +27-11-899-2373 or email basemetals@batemanengineering.com.
VIEW
PDF
©
Copyright BATEMAN 2004