Feasibility study completed for Doris North at Miramar's Hope Bay

 

 

The mesa of the Doris North Zone where the mill will be located.

Materials for the construction of the mill will be brought to the Doris North Zone via Robert's Bay (shown above).


BATEMAN has been contracted by Miramar Mining Corporation to investigate the potential to install an SAG (semi-autogenous grinding) mill to reduce capital and operating costs on the proposed initial development of the high-grade Doris North gold deposit at the Hope Bay project in Nunavut, Canada.

This investigation is an extension of a feasibility study conducted by BATEMAN with other consultants, which was completed in 2003, with the objective of facilitating the rapid development of low-cost, high-return and low-risk gold production on the Hope Bay belt. Based on the results of this study, production on the Doris North deposit is targeted to commence in early 2006, subject to the granting of the required permits.

The mining of the Doris North Zone will be by underground methods, with ore hauled from underground by truck to a crusher located adjacent to the portal feeding a modular milling plant pre-constructed off site and transported to site in assembled units.

A modular concept was selected for the study as no foundations would be required for the mill, which could be set on bedrock and compacted fill and covered with a sprung structure similar to those used at a number of other arctic locations. The ore will undergo conventional crushing and grinding with an integrated, gravity, gold-recovery circuit followed by flotation and cyanidation of flotation concentrates, with gold dorŽ produced on site.

The mining resources defined within the study comprise the Doris Hinge and portions of the Central and Lakeshore veins in the limbs of the Doris Hinge vein. The feasibility study was prepared on the basis of developing the facilities for a longer-term operation than the expected two-year lifespan of the Doris North deposit, as there is significant potential to extend the mine's life through the development and mining of other resources in the Hope Bay belt. The mill was therefore designed for a maximum throughput of 800 t/day to accommodate possible future increases in throughput, even though the feasibility study considered an average throughput of 668 t/ day.

The BATEMAN modular gold-process plants for the extraction and recovery of gold are particularly suited for fast-track operations and for remote sites where construction is difficult. This is due to the fact that the plants are designed, fabricated, trial erected and water commissioned in the factory and then partially dismantled for transport to site where they can be rapidly re-assembled and commissioned.

Pre-concentrating the gold into a small volume of concentrate that can be intensively treated is another key feature of the BATEMAN modular gold plants. This feature leads to a more compact operation; minimised reagent exposure, containment and elimination; reduced leach times and circuits; and possible direct gold recovery via electrowinning, thus avoiding carbon adsorption, stripping and regeneration.

Please contact Dr Peter Spencer, General Manager, Gold on +61-9316-6905 or e-mail gold@batemanengineering.com for more information.

VIEW PDF

© Copyright BATEMAN 2004