Tailings stacking system with
the rail-mounted spreader on
the tailings dump.

Above: The circular-stacker-bridge reclaimer is contained within a 93 m diameter dome (the exterior of which is shown below) for environmental protection, making this the first such installation in southern Africa

Total materials-handling system completed for Skorpion Zinc

BATEMAN has successfully completed three major contracts at Anglo American’s Skorpion Zinc Mine and smelter complex in southern Namibia, covering the design, construction and commissioning of a complete materials-handling system to move ROM (run-of-mine) ore to the plant and the resultant tailings onto the waste dump.

In all, 18 conveyors were needed to construct the system which totals 5,9 km in length and includes a 3 km overland conveyor carrying the tailings. The project included the design and supply of the all necessary transfer towers, the primary and secondary crushing and screening buildings, and the ROM and limestone grizzlies and bins. All free-issue equipment, such as rock breakers, vibrating grizzlies, crushers and screens, were installed by the BATEMAN project team.

Two of the outstanding features of the system are the completely enclosed ROM stockpile and the tailings dump. The 50 000 t ROM stockpile is equipped with a BATEMAN / SCHADE circular-stacker-bridge reclaimer. Designed to blend the ROM, it stacks at a rate of 460 t/h and reclaims at 380 t/h. The 85 m-diameter stockpile is contained within a 93 m diameter dome for environmental protection, making this the first such installation in Southern Africa – if not the Southern Hemisphere.

The self-supported, shell-designed dome would almost cover a rugby field. It is constructed from 9 800 m² of 0,6 mm Chromadek sheeting. Maintenance access is provided via four 5 m x 4,5 m roller-shutter doors. The dome becomes a homogenous self-supporting shell, which relies upon membrane action for its overall stability. Special consideration was given to the method of erection in order to maintain stability at each stage prior to the onset of the membrane action.

The design of the tailings dumps is beset with problems ranging from those associated with the environment, slope stability and spreading methods, to choice of equipment and operational efficiency. Working closely with the Skorpion project team, and drawing on past experience in designing tailings spreader systems at Mantos Blancos in Chile, Damtshaa in Botswana, and Transhex and Venetia Diamond mines in South Africa, BATEMAN presented a workable solution.

A three-way transfer tower at the head of the 3,5 km overland conveyor distributes tailings onto a 550 m conveyor prior to feeding them onto a rail-mounted tripper and into a slewing 25 m-long spreader boom. The transfer tower caters for future dump positions and permits the utilisation of the emergency dump conveyor during times of maintenance and other plant shut downs.

BATEMAN made maximum use of local labour during this project which was particularly challenging due to the location of the Skorpion site, some 40 km north of the Orange River and deep in the Namib desert, and the extreme climate. Yet, despite these conditions, BATEMAN completed the project on schedule with an accident-free record.

For further information contact

Eric Fletcher, Marketing Manager, Bulk Handling, on
+27-11-201-2300 or email engtech@batemanengineering.com.

VIEW PDF