|
First tap of ferrochrome at SA Chrome
|
|

The chute with solidified slag after the tap.

SA Chromes first
batch of charge
ferrochrome
pouring out of the
furnace.

The taphole drill being positioned to drill the first taphole on the
furnace.
|
SA Chromes first furnace at the Boshoek site near Rustenburg,
RSA, was fired up on 9 June 2002, with the first tap of charge ferrochrome
being tapped on 13 June.
By mid July, less than one month later, when
100 taps of metal had produced 2 800 t of saleable product, the furnace
had already been ramped up to a power consumption of 48 MW.
This greenfield plant has been installed in the remarkably short time
of 15 months, the contract for the SA Chrome smelter having been awarded
to BATEMAN at the end of March 2001 and the first steelwork having been
erected on site a mere four months later.
When completed, the smelter will consist of two 54 MW closed submerged
arc furnaces and a pelletising and sintering plant to process 520 000
t/y of a blended feed of chromite and chrome concentrate.
The next major components on the project schedule are the second furnace
and the sinter plant producing a feed of sintered pellets for the furnaces.
Construction is progressing well and commissioning should be completed
by the end of August.
For more information, please contact George Farmer,
General Manager, Bateman Ferrous, on +27-11-899-2531 or email ferroalloys@batemanengineering.com
VIEW PDF
|