The building housing the two furnaces has reached a height of over 60 m.



A refurbished crusher being installed at the left, with the sinter building under construction in the background.

Safety on track at SA Chrome

On 28 February 2002, the site personnel installing the R700M turnkey ferrochrome smelter for SA Chrome at the Boshoek site near Rustenburg, RSA, celebrated the significant achievement of half-a-million manhours without a lost-time injury.

The activities at the site have recently been ramping up rapidly, and the 1 286 persons on site during the celebrations will increase to a peak of about 1 500 during mid-March,” explained Jonathan Such, Senior Project Manager. “The preservation of life and limb is our prime objective, so it is always with a sense of relief and satisfaction that we achieve these important safety milestones during large projects.

“Accordingly a comprehensive safety campaign led by the project’s safety consultant is maintained,” said Such. “This involves induction training for all new personnel on site, lectures on safety and tool-box talks. To further promote ongoing vigilance, a safety competition based on the comparison of regular safety audits is organised between all of the main contractors.”

The site’s staff complement comprises mainly semiskilled and unskilled labourers, with a few artisans. In terms of the project contract, the use of local labour has been maximised, with a large proportion of the personnel having being drawn from the local labour market. There are about a dozen large contractors on site, providing services in respect of civil, mechanical erection, piling, structural, electrical-instrumentation and specialist-refractory installations.

“Aside from three days lost, due to inclement weather which resulted in the temporary flooding of portions of the site, good advances have been made on the construction and we are well positioned to put up a record time for this type of project,” claimed Such. “From the time the first steel was erected in early August 2001 to now, more than 4 000 t of steel have been delivered to site and 3 200 t erected. The civil works have required 710 piles to be placed, 61 000m³ of ground excavated, 125 000m³ of soil replaced, 60 000 m³ of concrete poured, utilising 18 000m² of shuttering, and 1 200 t of reinforcing steel and 4 500 m of piping have now been installed. The main furnace building has topped out at 60 m high and towers over the surrounding landscape.”

For further details kindly contact:

George Farmer, General Manager, Bateman Ferrous,
on +27-11-899-2531 or email ferroalloys@batemanengineering.com

VIEW PDF