
Part of the flotation plant
supplied to Impala's UG2 site,
Rustenburg, RSA.
|
Flotation at Impala Platinum's UG2 plant
BATEMAN has supplied and commissioned 21 flotation cells to Impala
Platinum Limited for the UG2 Ore Separation Project. The flotation circuit
is successfully treating a combination of high- and low-grade UG2 ore
to separate a platinum bearing concentrate from the gangue material
containing chromite.
Although cost was the main deciding factor, the BATEMAN flotation cells
were selected by Impala after taking into consideration the design features
of the cells, which promised to overcome difficulties which had been
encountered previously on other UG2-ore flotation circuits.
The circuit consists of four high-grade rougher cells with a 50 m 3
capacity, seven low-grade rougher cells (50 m 3 ), six low-grade cleaner
cells (20 m 3 ) and four low-grade recleaner cells (10 m 3 ). BATEMAN
supplied all the control equipment for the flotation circuits, including
the level- and air-control instrumentation.
As with all BATEMAN flotation circuits, the cells as well as the feed
and transition arrangements between adjacent cells were custom designed
for this application. The first cell in each flotation bank has an integral
feedbox, semi-circular in shape, which minimises the delivery distance
into the cell. The feedboxes are sloped to ensure a continuous flow
of material and a slotted inlet into the cell eliminates any chance
of the inlet becoming blocked.
The level of the slurry in a cell is controlled by means of two actuated
dart valves positioned internally to ensure that the area around the
cell outlet is kept clear, thereby reducing the possibility of chokes.
The discharge from the dart valves is through semi-circular dart boxes
located under the cell. These boxes are sloped towards the outlet to
maintain a sufficient flow into the following cell.
The design also permits efficient pumping through the rotor-stator combination
without causing turbulence at the pulp-froth interface. Additionally,
the mechanisms are able to suspend the chromite particles in a fluidised
bed to ensure a satisfactory flow through the cell.
Target-plate and float-type level assemblies were also supplied, together
with an ultrasonic-level detector for integration with the dart valve
actuators. Flow meters and butterfly valves were fitted to control the
air supply into the cells and four Roots-type blowers provide the air
supply to the flotation circuit.
During commissioning, all of the cells were started up initially with
water and air and then slurry was introduced. The circuit operated from
the start without any problems. Once in operation, the level and air
control was fine tuned in order to ensure optimum operation of the complete
flotation circuit.
This project commenced in May 2000 and was completed in May 2001. Once
steady state conditions were established, is was possible to commence
maximising the performance of the circuit by optimising the control
of the levels in the cells, the reagent additions and the air supply.
Optimisation work is ongoing.
Please contact Craig Gilbert, Manager, Processing Technologies, on +27-11-201-2300
or email specialised@batemanengineering.com
for more information.
VIEW PDF
|