

A 3D CAD rendering of the spiral circuits of the Hillendale primary wet-treatment
plant. The banks of spirals are shown in green at the top of the plant,
with the control room and motor control centre (both in red) on the left
below the spiral banks.

The feed preparation module with its rotating trommel screen.

The first concentrate being stockpiled by the stacker.

Distributors at the top of the
spiral plant.
|
Hillendale heavy-minerals plant
A primary wet-treatment plant to process mineral sands, designed
by BATEMAN for Iscor Heavy Minerals (Pty) Ltd (now Ticor South Africa),
has been commissioned and is operating successfully at Hillendale, close
to Richards Bay in South Africa. BATEMAN, the managing contractor on
the project, was responsible for the engineering design, project management
and construction supervision, which were carried out under a lump-sum
contract. BATEMAN was also responsible for the commissioning, which
was done in terms of a reimbursable contract.
Work on this R70 million contract for Hillendales wet-treatment
plant started in August 1997, with the design being completed by May
1998. Construction commenced in May 2000 after the finances for the
project were secured. The plant was completed in April 2001. Performance
guarantees in respect of the rate of solids throughput, product grade
and mineral recovery were complied with.
The 1 200 t/h wet-treatment plant effectively separates gangue material
in the run-of-mine ore to produce a heavy mineral concentrate, containing
ilmenite, rutile and zircon, which is transported in covered trucks
to the clients central processing complex at Empangeni, about
15 km away, for further processing.
The plant is designed to be movable and comprises modules, for feed
preparation, spiral separation, thickening and stockpiling the heavy
mineral concentrate. These can be dismantled into components that are
small enough to be transported by road to a new location when the need
arises. Dismantling will be facilitated because all tanks are flanged
and the structures spliced at strategic positions. The flocculant plant,
motor-control centres (MCCs) and switchgear assemblies were supplied
in standard containers for easy transport.
The process involves mining the heavy-mineral-bearing sand using highpressure
water jets, and pumping the resulting slurry to a rotating trommel screen
where the oversized waste material, mainly vegetation, is removed. The
undersize material is collected in a constant-density surge tank where
the slurry is densified and then diluted to a predetermined density
required by the spiral circuits. In these circuits, the heavy minerals
are separated from the lighter gangue utilising their difference in
specific gravity. After removal of the magnetite from the spiral concentrate,
using a low-intensity magnetic separator, the concentrate is pumped
to a dewatering cyclone mounted at the end of the stacker and placed
directly on the stockpile. From here the concentrate containing about
5 % moisture is trucked to Empangeni. Sand tailings from the spiral
circuits are pumped to the dune rehabilitation area for backfill. Slimes
produced by the wet-treatment plant are thickened and separated from
the process water using ultra-high-rate thickeners. The supernatant
liquor
from the thickeners is recycled as process water.
The plant comprises a large amount of gravity-feed piping that required
careful design, particularly the spiral circuits where the material
gravitates through primary, secondary and tertiary stages to separate
the heavy minerals. In these circuits a considerable amount of steelwork
is needed to support the HDPE (high-density polyethylene) piping which
is used extensively to minimise corrosion.
The contract was awarded to BATEMAN because of its competitive bid,
experience and expertise with this type of plant. The work was completed
on schedule and the start-up of the plant proceeded more smoothly than
is usually achieved for this type of installation. The clients
personnel expressed their satisfaction with the plant.
More details may be obtained from:
Vincent Diesel,
Project Manager - Special Projects, on +27-11-899-9111 or
email vdiesel@bmi.co.za
VIEW PDF
|