CADD generated plan of the primary wet treatment plant designed for Iscor.


Heavy minerals treatment plant for Iscor

Bateman Minerals and Industrial Limited has completed the conceptual and detailed engineering of a 1 200 t/h primary wet treatment plant for Iscor Heavy Minerals to be built at the Hillendale site near Empangeni, RSA.

The Primary Wet Treatment Plant (PWP) will separate the gangue material in the run-of-mine-ore to produce a heavy minerals concentrate (HMC). The HMC containing ilmenite, rutile and zircon will be transported to the Minerals Separation Plant (MSP) for further processing.

Details of the process are as follows. The heavy mineral bearing sand is mined using high pressure water jets. The resulting slurry is pumped to a rotating trommel screen where the oversized waste material, mainly vegetation, is removed. The trommel undersize material is collected in a constant density tank where the slurry is densified and then diluted to a predetermined density. The slurry is then pumped to the spirals circuit where it passes through five stages of spiral concentration to separate the heavy minerals from the lighter gangue. After removal of the magnetite using a low intensity magnetic separator the HMC is pumped to a cyclone mounted at the end of the stacker. There it is dewatered and placed directly on the stockpile from where it is trucked to the MSP. Sand tailings from the spirals circuit is pumped to the dune rehabilitation area as backfill. Slimes generated by the PWP are thickened and separated from the process water using ultra high-rate thickeners.

Several aspects of this project contributed to its complex nature. The plant comprises a large amount of gravity feed piping which required careful design. As HDPE (high density polyethylene) will be used extensively in the spirals circuit to minimise corrosion, the design also required a considerable amount of supporting steelwork for the HDPE piping.

After three years of operation the plant will have to be moved to a new site 2 km away. This has been catered for in the modular design which will enable the major components such as the trommel screen, the spirals buildings, 12 m diameter thickeners, pipe racks and the stacker to be moved as separate units with minimal uncoupling of piping and other gear. About seven years later a more difficult move to a site 39 km distant is envisaged, possibly requiring the plant to be broken down into even smaller components no larger than 7 to 8 m in height to comply with road transport restrictions. As a result all tanksare flanged and the structures have splices to permit dismantling. Some items such as the flocculant plant, motor control centres (MCCs) and switch gear assemblies are to be supplied in standard containers for easy transport. These items will be fully assembled and pre-tested off-site before delivery.

This phase of the work was awarded as a lump sum contract to BATEMAN in August 1997 and took about one year to complete. BATEMAN’s responsibilities included the process engineering and the structural, mechanical, piping, electrical and instrumentation engineering and design.

Iscor envisages that the next two phases of the project could commence after mid-1999 which will involve the inspection and expediting of the equipment, construction management and hot commissioning of the plant. Should Iscor proceed, BATEMAN will handle phases two and three of the project.

Please contact Vincent Diesel, Director Special Projects,
on +27-11-899-3213 or

email: industrial.minerals@batemanengineering.com

VIEW PDF