|

The stacker conveyor leading out of the crushing plant.

An overview of the process plant at Gunpowder Copper, with the oxygen
generation plant in the left foreground, the reagent plant in the centre
foreground in front of the leach circuit and the Delkor filter in the
centre background. The electrowinningand solvent extraction circuits are
in the background on the right of the picture.

The grinding and thickening circuits in the centre of the picture, with
the crushing plant in the background on the left.

The leach plant with the autoclave on the left and the leach tanks on
the right of the picture.

The leach liquor is filtered on this Delkor horizontal belt filter. It
has an area of 158 m 2 with a counter-current wash configuration and is
the largest of its type in the world.

The autoclave equipped with five agitators in which the ore is subjected
to a low temperature pressure leach. This is the first time this process
has been applied to a copper ore.

The interior of the electrowinning tank house in which high gradeLondon
Metal Exchange copper is produced.
|
Gunpowder Copper project successfully completed
Bateman Kinhill is in the final stages of the project to expand
the existing copper cathode production capacity at the Gunpowder copper
mine recently acquired by Western Metals Limited.
The expanded plant
The expanded plant will process 750 000 t/yr of chalcocite ore from
an opencast operation mining the Esperanza ore body, typically containing
7,5 % copper, to produce 50 000 t/yr of high grade LME (London Metal
Exchange) copper.
The ore is crushed in a jaw crusher and ground in a semi-autogenous
(SAG) mill and then subjected to an acidic ferric sulphate leach in
combination with an autoclave operating at low temperature and pressure.
This is the first time this process has been applied to copper. The
leach residue is thickened and filtered for disposal. The leach liquor
is clarified, filtered and passed to the solvent extraction and electrowinning
(SX - EW) circuit. The acidic rafinate from the SX - EW circuit is recycled
to the leaching circuit.
To extract the copper in the leach liquor, BATEMAN reverse-flow enhanced
coalescence mixer settlers were installed in the solvent extraction
section. Similar units are operating successfully at La Caridad, Nacozari,
Mexico; Sanyati Copper, Zimbabwe and at the El Arco pilot plant, Baja
California, Mexico and have also been incorporated into the Bulong Nickel
project. This type of mixer settler offers a higher process efficiency,
reduced loss of organic solvent, lower capital cost, shorter construction
time, a more compact layout and easier operation than conventional equipment.
The old plant
The old plant, which processed Mammoth ore containing about 4 % copper
obtained from an underground mining operation, had a production design
capacity of 13 000 t/yr and has been incorporated into the new plant.
Project details
The design of the expanded plant was completed by a team of 65 people
in 7 months. The basic engineering package comprised a process flowsheet
which was developed jointly with Aberfoyle. Other process routes were
eliminated and all materials of construction were critically evaluated
and selected. Critical areas to permit a fast track project were identified
and long lead items specified and ordered.
Bateman Kinhill personnel assisted in the pilot plant operation during
which a close working relationship was established with Aberfoyle personnel.
Significantly, the team which was assembled for the project was based
on the study team.
The fast-track project commenced in July 1997 with a site management
team of 10 supervising 340 contractors and personnel. Construction was
essentially completed within an 11 month schedule at a capital budget
of Aus$92M. Dry commissioning started during June 1998 with electrowinning
commencing in August. The project team executed 110 construction and
procurement packages, poured 8 600 m 3 of concrete and installed 1 200
tonne of structural steel, 70 km of electrical cable and 32 km of piping.
Project cost
The total cost of the project was Aus$125M and it included the mine
development, power supply and infrastructure.
More information on the project may be obtained from Tony Cau, General
Manager, Base Metals, on +61-7-3320-3333 or email basemetals@batemanengineering.com.
VIEW PDF
|