|

Construction of the primary processing circuits with the stockpile
conveyor in the foreground, the mill feed conveyor in the centre, the
grinding circuit on the right and the thickening tanks in the centre background
and tailings dams in the far background.
|
Gunpowder expansion project
Bateman Kinhill, the EPCM contractor, is making good progress expanding
the existing copper cathode production capacity at Aberfoyle Limiteds
Gunpowder copper mine from its present 8 000 t/yr to 45 000 t/yr .
The process involves tank leaching of chalcocite ore in combination
with an autoclave operating at low temperature and pressure. This is
the first time this process has been applied to copper. Leaching is
followed by solvent extraction in BATEMAN patented reverse-flow mixer-settlers
and then electrowinning to produce high grade copper cathode.
The Bateman Kinhill team has handled the tight project time-frame well
and to date has executed 104 construction and procurement packages,
poured 8 600 m 3 of concrete and is installing 1 100 tonne of structural
steel, 70 km of electrical cable and 33 km of piping.
This fast-track project commenced in July 1997 and is currently on schedule
to meet its 11-month target. Dry commissioning is due to commence during
June with the first cathode due to be produced early in August. The
project is expected to finish within its capital budget of Aus$92M.
Further details are available from Tony Cau, General Manager,
Base Metals, on +61-7-3320-3333 or email basemetals@batemanengineering.com.
VIEW PDF
|