Part of the concentrator’s
milling circuit.



The flotation plant (foreground) and grinding circuit.



The flotation and concentrate filtration areas.



The Modikwa commissioning team (left to right): Rhynhardt Huygen (Anglo Platinum Commissioning Manager) and from BATEMAN, Colin Kaiser, Johan Kruger, Wilhelm de Beer, Dave Allick, Hennie van Rooyen, Jeff Stevens and Simon Moses.

Modikwa UG2 concentrator commissioned successfully

Hot commissioning of the Modikwa (formerly Maandagshoek) UG2 concentrator was successfully completed during the second half of 2002, on behalf of Anglo Platinum Management Services (Pty) Ltd. The plant is located in RSA’s Northern Province, approximately 30 km northwest of Burgersfort on the road to Polokwane (formerly Pietersburg).

BATEMAN process and mechanical engineers were part of the integrated-commissioning team reporting to the client’s commissioning manager. BATEMAN provided assistance with the hot commissioning through to October 2002. The transfer to the operational team from the hot commissioning phase was made seamlessly utilising a new initiative from Anglo Platinum Projects. A team of process engineers from the projects group was put in place to direct the early operational phase with full on shift accountability until steady operations had been achieved. The very successful commissioning phase was thus built upon with a smooth transition to operations – the impressive plant capacity ramp-up and very high plant uptime figures reflect on the successful inputs from all three parties: BATEMAN, Modikwa and Anglo Platinum Projects.

The cold-commissioning phase commenced during May 2002 and in the first week of August the first ore was fed to the primary mill and the ball charge of the mill then gradually increased to full capacity. The ramp-up of the tons milled at the new plant went very smoothly. In August, 51 % of the design throughput of 200 000 tons per month of run-of-mine (ROM) UG2 ore was achieved and this increased to 101 % in September and 109 % in October.

naturally occurring, PGM-rich, fines fraction in the ROM ore to be separated ahead of the primary milling circuit and to be processed in a dedicated flotation circuit. In addition to the primary mill, there are two, separate, regrind mills, each with flotation circuits.

The flotation concentrate is fed to a high-rate thickener and dewatered in a horizontal-plate filter. The final product is dispatched in trucks. The flotation tailings are thickened in a high-rate thickener and pumped through an overland pipeline to the tailings dam.

A control-budget estimate for the project was completed by BATEMAN in August 1999 and the overall project approved in December 1999. BATEMAN provided the engineering services, including the implementation of the process design, and Anglo Platinum the contract management services. The joint team operated out of the BATEMAN offices in Boksburg.

For more details, please contact

Jeff Stevens, Principal Process
Engineer, on +27-11-899-3199 or
email jeffs@bmi.co.za.

VIEW PDF